| 182 | == MSP50.3 == |
| 183 | [wiki:MSP503 MSP50.3] |
| 184 | |
| 185 | This segment covers the period from 5 July 2024 to 30 September 2024 (end of the science operations). The Bryant plot is available at: http://jsocwiki.rl.ac.uk/attachment/wiki/WikiStart/bryant_msp_v5010_Dayside_2024.pdf |
| 186 | |
| 187 | This segment inlcudes SC2 re-entering date (8 September 2024) and science planning for September 2024 will be only for SC134. |
| 188 | It is agreed that on SC2 planning will be based on the assumption that some payload on SC2 will be ON (FGM, PEACE, WEC) but this might not be the case. |
| 189 | |
| 190 | Baseline telemetry is 140%. |
| 191 | |
| 192 | The segment includes a season of ‘Long Eclipses’ in September - November 2024 when all instruments will be switched off. |
| 193 | The estimated preliminary dates for the payload to be off during the Long Eclipse season are: |
| 194 | |
| 195 | * SC34 16/09/2024 09:00 - 30/09/2024 16:00 |
| 196 | * SC1 29/09/2024 16:00 - 07/11/2024 20:00 |
| 197 | |
| 198 | There will be moon eclipses on SC34 in September 2024, the eclipse time is 02/09/2024 17:12 - 02/09/2024 18:46. The payload constrains time is TBD. |
| 199 | |
| 200 | There are no manoeuvres in this segment. |
| 201 | |
| 202 | Cluster crosses the predicted magnetopause until: SC34 - 01/07/2024, SC1 - 03/07/2024, SC2 - 08/07/2024. |
| 203 | Cluster crosses the predited neutral sheet from: SC34 - 01/08/2024, and there are no predicted NS crossings on SC12. |
| 204 | |
| 205 | The main science targets are conjunctions between Cluster and MMS and/or THEMIS in the plasma sheet, and auroral acceleration region in the northern hemisphere. |